FROM THE NGS FIELD NOTEBOOK

Steep Excavation next to Brick Wall

Noorzay Geotechnical Services is working with another engineering firm to provide recommendations for temporary excavation. The excavation is supposed to be 3 feet deeper and cut into the side bench another 4 to 5 feet. We ran direct shear testing on relatively undisturbed samples to see if the slope stability factor of safety would be adequate. It wasn't. Currently working on an economical solution to ensure the safety of the workers during excavation for the foundation work.

20170810_104620
20170810_104607
20170810_104516
20170810_103720
20170810_103718
20170810_103715